Introduction & Project Background
The One Dalton project site in Boston, Massachusetts is an approximately 28,544 square feet triangular parcel without existing structures (Figure 1) except for an underground loading dock for the adjacent Colonnade building. Elevations refer to Boston City Base Datum (BCB).
Figure 1- Aerial view of the One Dalton parcel.
The new development includes a 61-story hotel and residential tower with an at-grade footprint area of approximately 21,600 square feet and three levels of below-grade space requiring excavation to depths of up to 47 feet below site grades, with localized excavations to 55 feet, and supported on rock-socketed deep foundations.
Because of proximity to the Colonnade, supported on shallow foundations, the deep excavation required careful selection of wall and foundation construction methods and relatively stiff excavation support systems to limit ground movements and reduce likelihood of building damage.
Figure 2- Digital rendering of the One Dalton tower (OneDalton.com).
Subsurface Conditions
The site is located on filled land in the Back Bay neighborhood of Boston, Massachusetts. Subsurface soil conditions observed from boring explorations are summarized in Table 1 and illustrated in the subsurface profile in Figure 3.
The excavation for the new tower terminates within the marine clay deposit, which consists of a stiff, overconsolidated clay crust 10 to 12 feet thick followed by about 115 feet of softer, slightly overconsolidated to normally consolidated clay. The undrained shear strength of the clay crust is estimated to be about 1,500 to 1,700 psf whereas the soft clay undrained shear strength is estimated to be about 1,300 psf at the top and increases with depth.
Bedrock at the site is part of the Cambridge Argillite formation and the degree of weathering in the core samples ranges from fresh to slight with zones of tuffaceous Argillite. An altered Mafic Dike was encountered at some boring locations with degree of weathering ranging from slight to high. Unconfined compressive strength of the Argillite and altered Mafic Dike test samples range from 780 psi to 12,426 psi.
Figure 3- Soil subsurface profile.
Adjacent Structures
The adjacent Colonnade Building is a five-story concrete structure supported on shallow footings and pressure-injected footings (PIFs) bearing in the marine sand layer. Available drawings indicate design bearing pressures for the foundations closest to the excavation ranging from 6,100 to 7,500 psf. The excavation for the new tower extends approximately 20 to 25 feet below the bottom of the Colonnade foundations (Figure 4).
Figure 4- Planned excavation and adjacent structure foundation.
As part of the new development, the loading dock connected to the Colonnade was demolished and portions of the building’s foundations protruding into the site were saw-cut and removed.
New Tower Foundations and Excavation Support
The new tower is supported on rock-socketed load-bearing elements (LBEs) and secant piles. Figure 5 shows the foundation and basement wall plan layout with rock-socketed foundation elements in orange and wall elements terminating in clay in yellow (slurry wall panels) or blue (secant piles).
LBEs are reinforced concrete elements consisting of one or more rectangular slurry wall panels approximately 2.5 feet or 4 feet wide by 9 to 10 feet long. The exterior LBEs extend from ground surface into rock, the interior LBEs extend from the lowest basement level into rock. LBE rock socket lengths range from 10 feet to 19 feet with geotechnical compression load capacities up to 12,500 kips for a single rectangular panel and 16,500 kips for a cross-shaped element.
The rock-socketed secant piles along the Colonnade are 39 inches in diameter with an embedded W24x176 steel section and a 36-inch diameter rock socket. Rock sockets range from 5 to 8 feet long except for one element with a 13-foot long rock socket. Geotechnical compression load capacities range from about 1,300 kips to 2,000 kips per rock-socketed secant pile. The maximum geotechnical uplift capacity is about 1,300 kips (for the secant pile with the longest rock socket).
The LBEs, secant piles, and slurry wall elements are designed to resist the permanent soil, water, surcharge (construction and adjacent building), seismic lateral pressures, and the temporary loading conditions during excavation, bracing installation, and subsequent bracing removal.
The slurry wall panels are 2.5 feet thick reinforced concrete elements extending to El. -48 feet (approximately 18 feet below the bottom of excavation).
The secant pile wall is composed of overlapping 39-inch diameter piles with an embedded W24x176 steel section every other pile. These elements also extend to approximately El. -48.
The LBEs and slurry wall elements were installed from existing site grades using slurry trench methods. Each LBE panel was excavated under slurry using a clamshell bucket (in soil) or a hydromill (in bedrock). The steel reinforcement cage was then lowered into the hole and the panel was filled with 7,000 psi concrete using tremie methods. A wide-flange steel section was utilized as an end-stop in primary panels. LBE panels were installed in a sequence where no two adjacent panels were open at the same time, with consideration for concrete curing times.
The secant piles were drilled from existing site grades using a full-depth temporary casing and concreted prior to pulling the casing to minimize ground loss. Cased installation was used because the potential for loss of ground and the resulting settlement of the Colonnade were a major concern.
Figure 5- New tower foundation and basement wall plan.
Below-Grade Construction and Subgrade Elements
The original planned excavation and bracing sequence consisted of three to four main cuts, each about 10 feet to 13 feet deep. No additional bracing was initially planned below the bottom of excavation, and grouting under the Colonnade foundations was contemplated. Finite element analysis of the staged construction predicted a lateral deflection of the secant pile wall adjacent to the Colonnade of about 1.7 inch without the subgrade elements.
The predicted lateral deflection raised concerns about potential excessive settlement of the Colonnade. Further analyses indicated that additional lateral support below the base of the excavation, placed before the excavation reached the lowest level, could help control deflections. After discussions between the project team and the owner, and considering the construction schedule and equipment that would be available on site, it was decided that subgrade lateral support elements composed of unreinforced rectangular concrete slurry wall panels be installed below the bottom of the excavation to act as struts or buttresses to provide increased lateral support for the embedded portion of the wall.
Figure 6 shows the locations of the seven subgrade elements. Five elements, acting as buttresses, extend approximately 30 feet from the secant pile wall and terminate in soil to avoid lateral load transfer to other structural elements. The buttresses were sized based on skin frictional resistance between the concrete and the clay along the sides and bottom of the elements. The other two elements act as struts/corner braces extending from the secant pile wall to LBEs on the adjacent side.
Figure 6- Subgrade element locations.
The secant pile wall and foundation elements were installed from existing site grade prior to mass excavation. The first cut was performed to El. +2 feet and then the subgrade elements were installed from this elevation using slurry trench methods. For each subgrade element, a trench was excavated under slurry to El. -47 feet and tremie concrete was placed up to El. -31 feet. Cement bentonite was then used from El. -31 up to El. +2 to facilitate removal during mass excavation. Each subgrade element is 2.5 feet wide, 16 feet deep and composed of unreinforced concrete with compressive strength of 2,500 psi. Positive contact between the secant pile wall and subgrade element was achieved by using a clamshell bucket with one scalloped side that followed the surface shape of the secant pile wall.
After the subgrade elements were completed, the first level of bracing was installed prior to mass excavation below that level. Mass excavation was conducted in three stages of excavation followed by brace installation. Temporary internal bracing (corner and cross-lot bracing) was installed at El. +10, -3, and -16 feet, and consisted of 36-inch diameter steel pipe elements preloaded to 50% of their design brace load. The bottom of excavation was approximately El. -31 feet next to the secant pile wall. Figure 7 shows a cross section of the secant pile wall and subgrade element after the final excavation stage.
A 6-in. thick concrete mud mat was installed after reaching the bottom of excavation, after which temporary bracing removal and floor slab installation was done in three stages. Floor slabs were installed at El. -31, -11, and +4.4 feet.
Figure 7- Bracing and subgrade element configuration along secant wall pile.
Construction Instrumentation and Wall Performance
Foundation wall and Colonnade movements were monitored during construction using inclinometers, building survey reference points, and tiltmeters.
Inclinometers are used to measure the lateral movement of below-grade walls and deep foundation elements. Grooved inclinometer casings were installed within select slurry wall and secant pile.
Survey reference points were observed using optical survey to measure changes in vertical positioning of points located on the exterior of the adjacent Colonnade. The Colonnade Building owner also elected to install survey targets on the building exterior to provide real-time monitoring (15 to 30-minute intervals) using automated total station equipment.
Tiltmeters are used to measure the tilt angle of a surface about an axis, and were installed on the fifth floor of the Colonnade.
Inclinometers were read frequently when excavation was undertaken adjacent to the secant pile wall. Colonnade Building reference points were optically surveyed weekly. The automated total station equipment and the tiltmeters recorded data continuously and uploaded them to a web page for the project team’s use. Figure 8 shows the instrumentation location plan.
Figure 8- Project instrumentation location plan.
Figure 9 shows the lateral displacement profile at various stages of construction for an inclinometer located within the secant pile wall next to the Colonnade. The bottom of the excavation was reached at the end of August 2016 and the displacement profiles are shown through March 2017. The approximate vertical extent of the subgrade elements is also shown. By March 2017, six months after the maximum excavation depth was reached, the maximum lateral displacement was about 1.0 inch. The shape of the displacement profile shows the restraining effect of the subgrade elements.
Figure 9- Secant pile wall lateral displacement profile and approximate subgrade element location.
Figure 10 shows the settlement at survey points 101-BS-12 located along the column line nearest the excavation and 101-BS-30 located on the eastern side of the Colonnade, along with relevant construction stages. At 101-BS-12, secant pile installation resulted in about 0.4 inches of settlement. Excavation and bracing installation for levels 1, 2, and 3 (L1, L2, and L3, respectively) each added about 0.1 inch of settlement (total of 0.3 inches). Final excavation to the bottom elevation added another 0.2 inches of settlement. Further settlement occurred after final excavation. In total, the measured settlement at 101-BS-12 was about 1.1 inches. At 101-BS-30 on the other side of the Colonnade, the measured total settlement was about 0.2 inches.
Figure 10- Collonade building vertical movement (settlement, inches) at two survey point locations
(see Figure 8 for locations).
Conclusions
The deep excavation extended below the stiff clay crust that would have provided increased lateral support at the bottom of the wall. Removal of this stiff clay layer increased the risk of excessive lateral movement of the secant pile wall and settlement of the adjacent building. Staged construction analyses indicated that lateral wall support below the base of the excavation would limit movements if installed prior to mass excavation. Concrete subgrade elements were selected as the most feasible solution given the project parameters (e.g., schedule, mobilized equipment, and cost). Seven subgrade elements were installed to brace the secant pile wall below the bottom of excavation prior to mass excavation. The subgrade elements successfully limited the lateral deflection of the secant pile wall to about 1.0 inch and the settlement of the Colonnade foundations to about 1.1 inches. About 50% of the Colonnade settlement occurred during secant pile installation (i.e., before mass excavation).
Wall movements in deep excavations in soft soil can be controlled by providing a stiff lateral support system and added support below the bottom of the excavation should be considered to further stiffen the lateral support system. To be effective, such lateral supports should be placed prior to excavation and must be installed tight against the wall so that the supports are engaged immediately.
Acknowledgements
Owner: One Dalton Owner LLC
Owner’s Representative: AECOM Tishman
Architect: Pei Cobb Freed & Partners/Cambridge Seven Associates, Inc.
Construction Manager: Suffolk
Structural Engineer: WSP
Foundation Specialty Contractor: TREVIICOS
Should you wish to contact any of the authors, Mark Haley, Jean Louis Locsin and Jesse Siegel all work out of Haley & Aldrich, Inc's Boston office, which is located at 465 Medford St., Suite 2200, Boston, MA 02129. Their email addresses are as follows: mhaley@haleyaldrich.com, jlocsin@haleyaldrich.com, jsiegel@haleyaldrich.com.
Important: To be recognized as a BSCES member you must login using your BSCES assigned username and password.
Please note: BSCES membership is handled through ASCE but your BSCES log in information is different than your ASCE log in information. To update your contact information, please visit their Manage Your Account page.
If you have issues logging in or have additional questions regarding registration, please contact us at 617/227-5551 or bscesreg@engineers.org.
Supported by the staff of The Engineering Center Education Trust